Retrofitting an LED mesh screen onto an existing facade is decided by dead load, not by pitch. A P25 grid adds 8.2 kg/m² to a curtain wall that was designed without it; a P50 adds 1.54 kg/m². That single figure, measured against what the existing structure can accept, chooses your pitch, your mounting route and your budget before aesthetics enter the conversation.
The work divides into five surveys, three mounting routes and one structural decision nobody can delegate to a supplier. This guide sets out what each survey must produce, how the three routes differ in cost and risk, where the power budget usually breaks, and which line items a new-build quotation will never include. It ends with the approvals the building has to clear before any of it can be installed.
The decision you cannot delegate
Whether an existing facade can accept additional dead load, and at what point, is a structural engineer’s written opinion on that specific building. No supplier can give it, and no supplier should be asked to. Everything on this page is engineering context for that conversation — not a substitute for it.
1. Why an LED mesh screen retrofit is not a smaller new-build
On a new building the facade and the screen are designed together. The mullion spacing, the anchor points, the structural allowance and the cable routes are all decided while the curtain wall is still a drawing. On a retrofit, every one of those decisions was already made by someone else, years ago, without knowing a screen was coming.
The practical consequence is that a retrofit runs a different sequence:
2. The five surveys, and what each must produce
A retrofit survey is not a site visit. Each of the five has a specific deliverable, and the project cannot be priced until all five exist. Contractors who quote early usually quote against two of them.
Three misjudgements account for most retrofit problems, and all three are avoided by finishing the surveys before pricing:
| Misjudgement | What it looks like at the time | What it becomes later |
|---|---|---|
| “It is only a screen, it weighs very little” | A reasonable assumption from the P50 figure | A change order when P25 was designed and the structure rejects it |
| “The existing power has spare capacity” | Usually true at the board | A new transformer, riser and metering when the run is calculated |
| “We will fix the details on site” | Sounds like experience | Field joints in a sealed unit, and a facade warranty voided |
Survey 01 — Structural
Must produce: mullion spacing and section, anchor condition, the load case the allowance was checked against, the deflection limit it was verified to, and an allowable additional dead load in kg/m². That last number is the whole project. If the engineer returns 4 kg/m², the P15.625 to P25 family is excluded and the discussion moves to P50 without further debate.
Read the report for three things beyond the headline figure. Which load case it covers: dead load alone, or dead load with wind suction under EN 1991-1-4, which is the case a porous screen can still influence. Which deflection criterion it was checked to, because curtain wall mullions are commonly verified at L/175 of the span, and a mullion that passes on stress can still fail on deflection. And which sections of the elevation the figure applies to, since a value taken at the podium is not the value at the top of the tower.
Two details decide whether that allowance is realistic. The first is whether the figure is for dead load only or whether it has been checked against wind. An LED mesh screen is porous, and most of the wind passes through, but the screen plus its brackets still adds to the suction cases the facade was designed for. The second is where the load lands: an allowance averaged across the facade is not the same as capacity at the specific bracket positions.
Ask for the bracket position, not the average. A facade can have 12 kg/m² of average spare capacity and still fail at the anchorage, because the screen’s load is concentrated on a limited number of mullions. The engineer needs the bracket layout to answer properly — which means the mounting route has to be sketched before the structural answer is final, and the two decisions iterate.
When the drawings are wrong
The original architectural drawing is not a record of the building. Facades accumulate undocumented change — replaced panels, added penetrations, a previous lighting installation fixed with self-drilling screws, a section rebuilt after water damage — and none of it appears on the drawing issued at handover.
Three verifications belong in survey 01, and all three are physical rather than documentary.
| Verification | Method | What it decides |
|---|---|---|
| Substrate behind the fixing line | Core drilling at sample positions, or scanning where drilling is not permitted | Whether the anchor lands in steel, concrete or a cavity |
| Pull-out capacity at the actual position | On-site pull test to a multiple of the design load | Anchor type, edge distance, and the number of fixings per bracket |
| Movement and tolerance over the height | Measured elevation against a surveyed datum, plus the facade’s thermal movement range | Whether the frame needs slotted connections instead of fixed ones |
The tolerance question is the one that surprises contractors. Curtain wall tolerances accumulate: a ±2 mm panel tolerance at the base is not ±2 mm at 60 m, and a frame fabricated to nominal dimensions will not fit a building built to the upper end of its permitted deviation. Either the frame carries adjustment, or the survey measured the deviation rather than assuming it away.
Survey 02 — Electrical
Must produce: spare capacity at the nearest distribution board in kVA, available riser and conduit routes, the metering point that will be used for the client’s operating cost, and the earthing arrangement. On a facade retrofit the electrical survey usually finds more constraint than the structural one — existing risers are full, and no one wants to core a new penetration through a finished facade.
The other figure that gets missed is voltage drop over the run. LED mesh screens run on DC 24V or DC 12V, and low-voltage distribution over the height of a building loses a meaningful fraction of its voltage before it reaches the top. A screen that works in the factory test can fail to start at the top of a 60 m riser because the supply at the last module is below the driver’s minimum input.
The consequence is that “there is a spare 32 A breaker” is not an answer. What is needed is the conductor size over the actual route, the length of that route, and confirmation that the last module still receives its minimum input voltage at full load on the hottest day. The 3% figure that IEC 60364-5-52 works to for lighting circuits is the usual design limit, and on a DC 24V or DC 12V run the same percentage is a tighter absolute number than it is on mains.
Survey 03 — Geometric
Must produce: a measured elevation, not the original architectural drawing. Curtain walls move. Panel tolerances, cumulative deviation over 60 m of height, corner returns and movement joints all differ from the drawing, and a screen fabricated to the drawing will not fit the building.
Survey 04 — Access
Must produce: lifting position, whether a building maintenance unit exists or rigging must be installed, the public protection plan, and the permanent maintenance route for the screen itself. That last item is frequently forgotten, and it determines whether a failed module is a 20-minute swap or a scaffold.
The maintenance route question has a design consequence that should be settled before the mounting route is fixed. A screen mounted on an independent frame stands far enough off the facade to be reached from behind. A screen clamped directly to mullions may not, and if the only access is from the front, every maintenance operation becomes a rigging operation.
One question to ask in the survey
Ask where a technician stands to replace a single module in the middle of the screen, and how they get there. If the answer involves scaffolding or a suspended platform, the maintenance cost over ten years will exceed the price difference between pitches — and that belongs in the client’s decision, not in a footnote.
Survey 05 — Strip-out
Must produce: an inventory of what is being removed, the waste route, how openings will be sealed, and the making-good scope. If the retrofit replaces existing facade lighting, the strip-out is often the most disruptive part of the programme, not the screen installation.
3. Three mounting routes for an LED mesh screen, and what each costs you
The mounting route is determined by two facts from survey 01: whether there is a mullion to clamp to, and whether the structure can take the load where the mullion is. There are only three answers.
| Factor | Clamped to mullion | Independent frame | Panel replacement |
|---|---|---|---|
| Facade types | Unitised, stick | Any | Any, during replacement |
| Additional load | Screen only | Screen plus frame | Screen only |
| Structural design needed | Local check | Full frame design | Panel redesign |
| Programme | Shortest | Design time added | Longest |
| Watertightness risk | Low — no penetration | Medium — tie-back penetrations | High — panels opened |
| Reversible | Yes | Yes | No |
Clamping wins when
- Mullions are exposed and evenly spaced
- Local capacity checks out at the bracket line
- The client needs the facade untouched
Clamping fails when
- Laminated or frameless glazing
- Mullion spacing exceeds module width
- Local point load exceeds panel capacity
Mixed routes, and why they are more common than the table suggests
Real facades are rarely one system. A building may have a stick curtain wall on the podium, unitised glazing on the tower, and a frameless glass entrance canopy at street level. A single retrofit can legitimately use all three routes on the same building, and the budget should reflect that rather than forcing one route across the whole elevation.
Mixed routes cost less than a single-route budget implies, because design effort scales with the number of routes rather than with area. What they add is coordination: each route brings its own bracket, its own installation sequence and usually its own trade, and the interface between two routes is where water gets in and where the programme slips.
| Cost element | Clamped | Independent frame | Panel replacement |
|---|---|---|---|
| Brackets and fixings | Low | High | Low |
| Structural design | Local check only | Full frame design | Panel redesign |
| Site labour hours | Low to mid | High | Highest |
| Facade making good | None | Penetrations only | Full panel scope |
| Programme risk | Low | Mid — design lead time | High — weather dependent |
| Reversible at end of life | Yes, fully | Yes, with patch repairs | No |
What must never carry the load
All three routes share one rule that is not negotiable and is routinely broken on small retrofits: the screen’s weight goes to the mullion or to the primary structure, never to the glass.
Tempered glass is strong under a distributed load and weak against a concentrated one. A bracket bearing on a pane applies a point load the panel was never analysed for, and the failure mode is spontaneous breakage — which can occur weeks or years later, from a nickel sulphide inclusion that the added stress tipped past its threshold. The breakage is then attributed to the screen, correctly, because the screen is what changed.
The gap is part of the design
Keep 30–40 mm clear between the rear of the screen assembly and the glass. The gap is not tolerance. It lets cavity air move behind the modules so the glass is not heated by contact, and it is the space a technician needs to clean the glass and reach a module. A screen set flush against the glass fails on both counts, and the second failure is only discovered at the first maintenance visit.
This is also why adhesive fixing — structural silicone with UV-cured brackets — belongs to frameless shopfront glazing and not to a curtain wall elevation. On a single pane at ground level the load is small and the panel is accessible. On a 60 m elevation it is neither.
The order of the two decisions is what costs money. Fix the route the facade physically allows, then let the pitch follow from the load that route can carry. Fixing the pitch first and shopping for a route afterwards produces two budgets for the same facade, and the second one is always the expensive one.
4. The weight figure that picks your pitch
Set the allowable additional dead load from survey 01 against the published weights and the pitch range collapses immediately.
Two things follow, and both are commercially useful:
- A retrofit almost always lands on P50 or coarser. Not because the client wants lower resolution, but because the existing structure has no allowance for anything heavier. This is the single most common reason a retrofit ends up with a coarser pitch than the design team first sketched.
- The viewing distance rule protects you here. At P50, a minimum viewing distance of about 75 m applies at 1.5× pitch in metres. Most retrofits are on buildings viewed from 60 m or more, so the coarser pitch is usually acceptable in practice — but it must be checked against the closest realistic viewpoint, not the best one.
Viewing distance check. Minimum distance in metres is pitch in mm × 1.5 at the tight end, and pitch in mm × 2 for comfortable viewing. P25 gives 37.5 m to 50 m; P50 gives 75 m to 100 m. Measure from the nearest point a person can actually stand.
What the added load does beyond the bracket
Dead load is the figure the engineer checks first, but it is not the only effect. Additional weight changes deflection, and deflection is what the seals were detailed against. A mullion verified at L/175 was verified for a total, and screen weight consumes part of that total: the structure can pass on stress and still push serviceability deflection past what the gaskets and sealant joints were designed to accommodate.
This is why a retrofit on a facade with a short remaining service life is often poor value, and why the structural report should state the age and condition of the seals alongside the load figure. Adding 1.54 kg/m² to a sound facade is a small change. Adding it to a facade that is already at the end of its seal life accelerates a problem that was going to happen anyway, and it will be attributed to the screen.
There is a third effect that a dead load check does not cover. A tall, slender facade responds dynamically to wind, and the screen adds mass at the outer face with its own natural frequency and its own fixings. On most mid-rise buildings this is negligible. On a tower, at a corner, or on a parapet where vortex shedding is already a consideration, the bracket detail becomes a fatigue detail rather than a static one, and the question for the engineer is not only whether it can carry the weight but whether it can carry it repeatedly for twenty years.
5. Power is the constraint nobody budgets for
Load is the constraint every retrofit brief mentions. Power is the one that surfaces after the screen has been chosen, and by then it surfaces as a change order: a new transformer, a new riser, or a lower configuration than the client already approved.
The electrical survey should return a spare capacity figure in kVA, and the screen is specified backwards from it. If the answer is 300 kVA — about 270 kW at a 0.9 power factor — then a 2,000 m² P50 facade at 240 kW fits and the two-RGB version at 576 kW does not. That decision is made on paper, before a purchase order exists, and it is the difference between using the board that is already there and building a substation extension.
Two items are missing from most retrofit electrical surveys. The first is a measured earth resistance: IEC 62305 assumes that a lightning protection and surge coordination study starts from an earth value someone has actually measured, and on an occupied building nobody has measured it since handover. The second is the condition of the existing distribution board, not just its spare ways. A board with no spare outgoing way, or one with a busbar at the end of its service life, is a replacement line item rather than a connection.
Injection points: the number that decides the cable schedule
A mesh screen cannot be fed from one end over a long run. Voltage drop accumulates, so the facade is divided into segments, each fed at one or more injection points. How many you need is a function of the pitch, the configuration and the height of the run — and it is the figure that determines how much cable the installer has to pull.
On a retrofit this is doubly binding, because the cable route already exists or does not. New injection points mean new penetrations through a finished facade, and each penetration is a weather seal to reinstate. A design that needs twelve injection points where the facade can accommodate four is not a design problem, it is a scope change.
Agree the injection layout with the survey
Ask for the injection layout drawing at quotation stage, not at shop-drawing stage. It is the document that reveals whether the electrical survey’s spare capacity is reachable at the positions the screen actually needs, and whether the cable route exists between them.
Heat in a sealed cavity
A screen on an independent frame has air on both sides. A screen set into a sealed curtain wall cavity does not, and the cavity is where the thermal budget is decided — not on the module datasheet.
Take the connected load from this section and treat roughly half to two thirds of it as heat leaving the modules and the drivers. A 2,000 m² P50 facade at 240 kW therefore has something in the order of 120–160 kW to dissipate inside a cavity whose only openings are the ones the facade already had. That heat raises module junction temperature, derates the drivers, and loads the sealant and the edge seal of any insulating glass unit on the other side of the gap.
| Question | Why the answer changes the design |
|---|---|
| Peak power density at full output, W/m² | Sets the heat load per square metre of cavity |
| Cavity temperature at the design summer ambient | Decides whether passive ventilation is enough and whether drivers need derating |
| Where the cavity vents, and whether it already does | A sealed cavity may need a vent path the facade was never detailed for |
| Temperature at the glass and at the sealant line | Insulating glass edge seals and structural silicone reach their limits before the LED does |
The consequence is that a retrofit can be structurally acceptable, electrically adequate and still wrong, because the cavity cannot shed the heat. Ask for the cavity temperature calculation at the same stage as the load calculation, from the same engineer, because the two use the same elevation and the same ambient assumptions.
6. Installing on a building that cannot close
Most retrofits happen on buildings that are occupied, in use, and cannot shut. This changes the installation method more than the product specification.
- Work hours. Drilling and core work falls outside operating hours on most occupied buildings, and night or weekend rates commonly run 25–50% above the day rate in the same market. Price the restricted hours at the restricted rate, not the programme at the day rate.
- Noise and dust containment. A retrofit on an operating building needs an enclosure around every drilling position, and that enclosure is a line item.
- Public protection. Anything dropped from height is a regulatory event. Over a street, this usually drives the choice toward pre-assembled panels lifted into place rather than component assembly at height — which pushes the order toward the finished-panel supply form.
- Sequencing with other trades. A retrofit competes with the building’s own maintenance programme for the same access equipment and the same hours.
Practical consequence
On an occupied building, buying finished panels instead of kits often pays for itself. The higher unit price is offset by fewer hours at height, less containment, and a shorter window of public exposure. Model both before defaulting to the cheaper unit rate.
Phasing: the option that avoids most of this
A facade retrofit does not have to be one programme. Splitting the elevation into phases lets the building operate normally through most of the work, and it lets the client see a finished section before committing to the rest. It also lets the installer learn the building on a small area before the difficult part.
Phasing has three costs, and they should be stated rather than assumed away:
- Access equipment is mobilised more than once, and mobilisation is a fixed cost per phase regardless of area.
- The screen was ordered in one run but installed in several, so the crate sequencing has to match the phase sequence, and any damage in phase one is discovered after phase two has shipped.
- Commissioning happens in stages, and the control system has to run partially populated without showing faults that do not exist.
On a building that genuinely cannot close, phasing is usually still the right answer. On one that can close for two weeks, a single concentrated programme is almost always cheaper.
7. What happens to the system you are replacing
Where the retrofit displaces existing facade lighting, the strip-out carries its own access, its own waste paperwork and its own making-good scope. It is also the line most often missing from the budget, because it belongs to no trade in the quotation.
| Removed item | Typical issue | Budget line |
|---|---|---|
| Linear LED fixtures | Drivers behind panels, not accessible | Access + re-sealing |
| Pixel point lights | Cable glued or clipped to facade | Adhesive removal, facade cleaning |
| Old control cabinets | Contain legacy DMX and power mixed | Disconnection, certification |
| Existing conduit | Not reusable, not removable | Abandon in place or strip |
| Penetrations | Sealant at end of life | Re-sealing and warranty |
Two questions decide the cost: can the old system be abandoned in place, and does removing it open the facade weather seal. If the answer to the second is yes, the re-sealing scope is a facade contractor’s work, not a lighting contractor’s.
Waste is the third question, and it is a compliance matter rather than a cost one. Removed luminaires, drivers and control gear carry electronic waste obligations in most markets, and on a commercial building that paperwork usually has to exist before the waste leaves site. Agree in advance who holds the waste transfer documentation, because the party that removes the material is normally the party that owns the obligation — whether or not they realised it when they priced the job.
8. Budget lines a new-build quote does not contain
A retrofit budget needs lines that never appear on a new-build quotation. Missing any one of them is how a retrofit overruns.
| Line item | Why it exists only on retrofit |
|---|---|
| Structural engineer’s report | New build has the allowance in the design |
| Measured survey of actual elevation | New build works from drawings that are correct |
| Independent frame design, if route 2 | New build ties into designed steel |
| Tie-back penetrations and re-sealing | New build has no existing weather seal to breach |
| Strip-out, waste removal, making good | New build has nothing to remove |
| Out-of-hours working premium | New build site is not occupied |
| Public protection and containment | New build has a hoarded site |
| Re-commissioning of existing controls | New build commissions a clean system |
Where retrofits overrun
The three largest overruns on retrofit projects are almost always the same: an independent frame that was not in the original budget, a strip-out scope larger than expected, and a power upgrade discovered after the screen was ordered. All three are survey outputs. None of them are supplier errors.
Rough proportions to sanity-check a budget
The ranges below come from MEKALEO’s own retrofit quotations. They describe the shape of a budget, not a benchmark, and the sample is small enough that they should be used to spot an outlier before submission rather than to build a price from:
| Element | Share of retrofit budget | What pushes it higher |
|---|---|---|
| Screen supply | 35–50% | Finer pitch, higher RGB configuration |
| Mounting and structure | 15–30% | Independent frame instead of clamping |
| Electrical works | 10–20% | New riser, new transformer, more injection points |
| Access and installation labour | 10–20% | Occupied building, out-of-hours working |
| Surveys and design | 3–6% | Complex facade, mixed routes |
| Strip-out and making good | 3–10% | Existing lighting to remove, seal remediation |
If a budget shows screen supply above 65% of the total, the installation and electrical scope has probably been underestimated. If it shows mounting and structure above 40%, the route decision is probably being made too late.
9. Feasibility checklist
Work through this before requesting a quotation. If any line is unknown, that is the next action rather than a reason to proceed.
- Allowable additional dead load in kg/m², in writing, from a structural engineer
- Mullion spacing and whether verticals are exposed and grippable
- Facade type: unitised, stick, laminated or frameless
- Closest realistic viewing distance in metres, measured on site
- Spare electrical capacity in kVA at the nearest distribution board
- Available riser or conduit route from that board to the screen
- Measured elevation, not the original drawing
- Lifting method and whether a BMU exists
- Strip-out scope and who owns re-sealing
- Whether the building can close, and for how many hours
10. Approvals: the part that delays the project
A retrofit changes the building’s external appearance and adds electrical load to it. In most jurisdictions that is two separate approval processes, and neither is run by the party installing the screen. They are the most common reason a retrofit that was technically ready in March installs in September.
| Approval | Triggered by | What the submission needs |
|---|---|---|
| Planning or facade alteration consent | Any change to the external appearance of the building | Elevations showing screen coverage and fixing method, and often a visual impact statement |
| Building permit | New structure, or new fixings into the primary frame | Structural calculations and fixing details, signed by an engineer qualified in that jurisdiction |
| Electrical approval | New connected load, a new board, or a new service | Single-line diagram, load schedule, protection coordination, earthing |
| Fire approval | Materials on the envelope, and any effect on openings, smoke venting or escape routes | Reaction-to-fire classification for housing and cabling, and a statement on openings |
| Signage or advertising consent | Commercial content, and in some cities any illuminated face | Brightness limits, operating hours, and the automatic dimming method |
Two of these have a design consequence rather than a paperwork one. Fire approval can turn on whether the screen obstructs an openable vent or a smoke outlet, and that is decided by the mounting route: a screen clamped across a vent bay is a different submission from one that stops at the transom. Signage consent sets a night-time luminance cap, which is a specification item rather than an afterthought, because the control system has to be able to schedule the reduction and evidence it.
Sequence the approvals against the screen order, not after it
The structural and electrical submissions need the mounting route and the connected load, which means the screen has to be specified to the point of a bracket layout and a kVA figure before anything is filed. A project that orders the screen first and applies afterwards is ordering a product it may not be permitted to install.
Where the retrofit displaces existing facade lighting, the fire and electrical submissions inherit the compliance position of what is being removed. That file is frequently incomplete, and the shortfall becomes part of your application. The site’s guide to fire inspection on glass curtain wall lighting covers what an inspector asks for on the existing installation.
FAQ
Can a mesh screen be fitted to an existing curtain wall?
Yes, on three routes: clamped to existing vertical mullions, carried on an independent frame tied back to the primary structure, or integrated into replacement panels. Which route is available is decided by the facade type and the structural survey, not by the screen specification.
Do frameless or laminated glass facades rule out a retrofit?
They rule out the clamped route, because there is no vertical mullion to grip. They do not rule out a retrofit. The project moves to an independent frame, which adds its own steel weight and design time, or to panel replacement if the facade is being renewed anyway.
How much weight does a mesh screen add?
From 10.2 kg/m² at P15.625 down to 0.78 kg/m² at P83.3. The commercially important step is between P25 at 8.2 kg/m² and P50 at 1.54 kg/m². On a retrofit, that step is usually what makes the project structurally possible.
Will a coarser pitch look acceptable on an existing building?
Usually, because retrofits are on buildings viewed from a distance. The check is pitch in millimetres multiplied by 1.5 to give minimum viewing distance in metres. A P50 screen is appropriate from about 75 m, which covers most street-level views of a mid-rise facade. Check the closest realistic viewpoint, not the most flattering one.
Does the electrical system always need upgrading?
Not always, but it is the most common late discovery. The screen’s connected load depends on the RGB configuration inside the chosen pitch — the published P50 range runs from 120 to 288 W/m². A 2,000 m² facade therefore draws between 240 kW and 576 kW. Get the spare kVA figure before specifying.
What is the biggest cause of retrofit cost overrun?
An independent frame that was not in the original budget, followed by a larger-than-expected strip-out scope and a power upgrade found after ordering. All three come out of surveys, which is why the survey stage should not be compressed.
Can the building stay open during installation?
Usually yes, at a cost. Out-of-hours working, dust containment around every drilling position and public protection over streets are all line items. On occupied buildings, pre-assembled panels frequently cost less in total than cheaper kits assembled at height.
What should the structural engineer’s report actually contain?
Four things in writing: the allowable additional dead load in kg/m², the load case it was verified against (dead load alone, or with wind suction under EN 1991-1-4), the deflection criterion used, commonly L/175 of the span, and the capacity at the actual bracket positions rather than an average across the facade. Ask as well when the facade’s seals and gaskets were last inspected, because added weight accelerates a seal that is already at the end of its service life and the failure will be attributed to the screen.
Send the facade type, the allowable additional load in kg/m², the closest viewing distance and the spare electrical capacity. MEKALEO returns the feasible pitch range, the mounting route, the dead load and the connected load at your configuration.
Scope, provenance and limits
Weight, power, transparency and brightness figures are taken from the published MEKALEO MDL-Grid specification table, revision November 2026. Structural and wind criteria are quoted as the limits your engineer will check against, not as findings about any particular building, and no figure on this page replaces a written structural opinion. The 4 kg/m² allowance in figure 4 is an example chosen to show where the cut-off falls. Budget proportions come from our own retrofit quotations on a small sample. The 30–40 mm clearance and the 50–67% heat conversion in section 5 are values commonly used in facade practice and a working approximation respectively, not findings about any specific project. The approval list in section 10 describes the categories that usually apply; it is not a statement of the law or the procedure in your jurisdiction. Last reviewed November 2026.
Load allowances are project-specific and must come from a structural engineer.
Project enquiry
Send your drawings. Get a specification you can defend.
Elevation DWG, facade area, closest viewing distance and site country — we reply within 48 hours with a fixture matrix, power and DMX topology, and a quotation. No price-only quotes.
5,000+ projects delivered · 40+ countries · ISO 9001 · CE / UL / RoHS