LED Facade Lighting RFQ: 12 Points for a Comparable Quote

By the MEKALEO engineering team — 22 years of LED facade production since 2004

A vague facade RFQ produces three incomparable quotations One sentence in, three prices out Same 800 m² facade, same building, three readings of the same sentence. The RFQ says “800 m² LED mesh screen” “P25” “IP66” “please quote” Each bidder reads it as screen area? or facade area? 2,800 nits? or 5,000? module IP? or connector too? zero spares? or 5%? Three quotes come back $88,500 screens only $96,000 screens + control $141,000 full scope The building never changed. The brief left gaps, so each bidder filled them with its cheapest assumption.
Three quotations for the same facade, priced against three different readings of one sentence.

Last updated: November 2026 | MEKALEO Engineering Team — LED media facade manufacturer since 2004

Three quotations for the same facade. One says $96,000, one says $141,000, one says $88,500. Nothing about the building changed between them. What changed is what each supplier assumed you wanted — and none of them told you what they assumed.

Quick answer: A comparable facade lighting quotation needs twelve inputs fixed in writing — facade and screen area separately, pixel pitch and viewing distance, daytime brightness, transparency and wind load, IP and corrosion class, control protocol, power distribution, mounting interface, quantities plus spares, delivery and commissioning scope, commercial terms, and acceptance criteria. Fix all twelve, and every supplier prices the same scope instead of their own assumption.

This is the normal outcome of a facade RFQ written as a shopping list. “800 m² of LED mesh screen, P25, IP66, please quote.” A supplier can answer that sentence truthfully and still leave out the controller, the power supplies, the mounting brackets, the spare modules, the sea freight, and the commissioning support. Six months later those omissions are change orders, and the cheapest quote becomes the most expensive project.

The fix is not more suppliers. It is a brief specific enough that every supplier prices the same scope. Below is the twelve-item structure we use when an RFQ arrives, followed by the drawings to attach, the commercial terms to lock, and how to read what comes back.


1. Why Most Facade RFQs Come Back Incomparable

A quote is only comparable if five things are identical across bidders: scope, specification, quantity, commercial terms, and exclusions. A typical RFQ fixes only the second one, and only partly.

Here is what we see in roughly nine out of ten first-round RFQs that land in our inbox:

What the RFQ saysWhat the supplier is free to assume
“800 m² LED mesh screen”Screen area or facade area? Finished screen at 24% transparency covers far more wall than 800 m²
“P25”P25 at which brightness? 2,800 nits or 5,000 nits is a different bill of materials
“IP66”Potted module only, or the connector and cable gland too?
“Complete system”Does complete include control, power, structure, cabling, commissioning?
“Delivery to site”Which Incoterm? FOB Shenzhen and DDP Rotterdam differ by 12–18% of order value
(no quantity of spares)Zero spares quoted, or 5%? On a 40,000-module job that is a five-figure gap
(no warranty terms)“5 years” against what failure criterion, with what response time?

None of these are tricks. A supplier answering an incomplete brief has to guess, and each guess moves the number. The purpose of an RFQ is to remove the guessing, not to collect prices.

2. The 12 Items in a Quote-Ready RFQ

Print this as a checklist. Every item that is missing from your RFQ becomes a variable in the price.

#Item to specifyWhy it changes the priceCommonly left out
1Facade area and screen area, separatelyDrives module count, structure, and freight volumeScreen area almost always
2Pixel pitch and viewing distancePitch sets density, weight, and cost per m²; overspecifying is the #1 overrunViewing distance
3Required daytime brightness (nits)2,800 vs 5,000 nits is a different LED bin and power budgetNight dimming requirement
4Transparency target (%) and wind loadTransparency and structural rating trade against each otherWind load (kPa)
5Ingress protection and corrosion classCoastal sites need marine anodising and a salt-spray reportDistance to coastline
6Control protocol and content sourceDMX512, SPI, or Art-Net; who supplies the media playerWho owns the content pipeline
7Power distribution conceptLoopback, number of feed points, voltage-drop allowanceCable runs and PSU locations
8Mounting interfaceCurtain-wall clip, steel subframe, or existing rail — structural steel is often 15–25% of the orderWho designs the bracket
9Quantities plus spares percentageSpares are priced once at order and again at year 4, at 3–5× the unit priceSpares entirely
10Delivery, installation and commissioning scopeWho unloads, who terminates, who does the night calibrationSite supervision
11Commercial termsIncoterm, currency, payment schedule, liquidated damagesIncoterm and payment
12Acceptance criteriaHow the project is judged: brightness uniformity, dead-pixel rate, colour consistencyDead-pixel threshold

Two of these deserve a longer note, because they are where most money is lost.

Item 1 — area. Always give both numbers. If you specify “1,200 m² of facade” for a P25 mesh at 55% transparency, you will receive a quote for roughly 540 m² of screen plus a structure sized for the full elevation — and you will spend the first project meeting arguing about which number was agreed. State screen area, and state the facade area it must cover.

Item 9 — spares. Facade modules are not shelf items in most countries. If you order zero spares and lose 1.5% of modules to water ingress in year three, you are buying a small production run at prototype pricing plus air freight plus a crew with a crane. Specifying 3–5% spare modules and 2% spare power supplies at order time is the cheapest insurance in the whole budget.

Both figures start from the same specification: pitch, transparency and weight per m². Our LED mesh screen range publishes those numbers model by model, which is how you convert facade area into screen area and module count — and size the spare allowance before anyone quotes.

Mark every input: confirmed, proposed, pending

A detail worth copying from construction procurement: tag each field in the RFQ with its status, so a supplier knows what it may question and what it must not change.

StatusMeaningSupplier’s freedom
ConfirmedFixed by the client, the consultant or a regulationMust meet it; may object in writing with a reason
ProposedA starting point the client will reconsiderShould propose better if it can, and explain why
PendingKnown to be missing; date expectedMust state the assumption it priced against
N/ANot applicable to this projectShould not invent a scope item for it

Without this, every gap looks the same, and suppliers fill gaps with whatever is cheapest for them. With it, a returned quote tells you exactly where the risk sits.

3. Who Is Responsible for What

The most common cause of a facade project running late is not a product failure. It is two parties each believing the other owned a work package. The RFQ is the right place to fix that, because it costs nothing to write down and a great deal to argue later.

Work packageWho must own itWhat goes wrong when it is unclear
Curtain-wall fixing designFacade contractor or structural engineerBracket clashes with the mullion; load path never approved
Lighting performance numbersLighting designer, or the supplier if asked explicitlyPitch and brightness decided by whoever quoted first
Structural subframeUsually the installer; sometimes the supplierEach side assumes the other, and the steel appears in no quote
Power distribution designElectrical engineer, with supplier input on voltage dropToo few feed points; visible dimming at run ends in year one
Control and content pipelineAV or control integratorNobody owns the media player; commissioning stalls for weeks
Site termination of connectorsSpecialist installer, or factory pre-terminationSite-terminated joints are where most ingress warranty claims die
Commissioning and night calibrationSupplier and installer jointlyFacade opens uncalibrated, with visible colour patches
Acceptance and baseline recordOwner or consultantNo baseline, so every later warranty claim becomes an opinion

Copy this table into the RFQ and ask each bidder to mark what it takes. The answers are more useful than the prices, because they expose which bidder has actually delivered a facade before.

4. Submittals: What a Serious Bidder Sends Back

A price is not a submittal. Ask for these with the quote, not after the order, and the comparison stops being about totals:

  • Mounting node drawing at the actual curtain-wall section, with fixing centres and torque values
  • Photometric files — IES or LDT for every optic offered, so the designer can verify the numbers independently
  • BIM object — a Revit family or CAD block at the mounting node, if the project has a BIM requirement
  • Wiring diagram — feed points, PSU zones, loopback arrangement, cable schedule per run
  • Test reports whose model numbers match the offered product: IP, salt spray, LM-80, and a 48–72 h burn-in record template
  • Packaging data — weight and volume per m², because freight on a 600 m² facade is a five-figure line and it depends on how the modules are crated
  • Warranty certificate draft, not a marketing claim about warranty
  • Spare parts list with part numbers, so replenishment in year four is a purchase order rather than a re-engineering job

Two of these decide whether the project can be commissioned on schedule: the wiring diagram and the BIM object. They are also the two most often missing from a first-round quote.

5. Drawings and Data to Attach

Text alone cannot produce an accurate facade quote. Attach these four, in this order of importance:

  1. Elevation with dimensions, marked with the area to be covered, and any zone where lighting must stop (fire exits, signage, adjacent property).
  2. Curtain-wall or cladding section detail at the mounting line. This single drawing decides whether the job uses a clip system or a steel subframe — and that difference is often larger than the difference between two fixture suppliers.
  3. Site photographs from the likely viewing positions, taken at night if possible. They settle the pitch and brightness argument faster than any datasheet.
  4. Structural and environmental data: design wind load, distance to coastline, ambient temperature range, seismic zone if relevant.

If you do not have item 2, say so in the RFQ and ask each bidder to state their assumed mounting concept explicitly. An assumption written down can be compared; an assumption buried in a price cannot.

A fifth input is not a document. Ask each bidder to price a mock-up — a 2–4 m² panel at the real mounting condition, one module bay, one power feed, one controller channel. Pitch, brightness, transparency and colour are judged together there and nowhere else, and on design-review projects its approval is a contractual hold point. A supplier that has never built one prices it as an extra; one that builds them routinely tells you where the panel should go.

6. Specify Performance, Not a Brand and Model

There is a strong temptation to paste a competitor’s model number into the RFQ so everyone prices the same thing. It feels rigorous. In practice it gets you either an exact copy at a lower price with unknown LEDs inside, or a polite refusal from suppliers who will not clone.

Write the requirement as measurable performance instead:

  • Brightness: 3,000 nits calibrated at 6,500 K, measured at module surface, with a night dimming floor below 300 nits
  • Colour consistency: within 3 SDCM across the delivered batch
  • Transparency: minimum 50% optical, measured on the installed module grid
  • Ingress protection: IP66 on module and connector, verified by test report matching the offered model
  • Salt spray: 500 h neutral salt spray to ISO 9227 for sites within 5 km of the coast
  • Lifespan: L70 at 50,000 h, LM-80 data for the LED bin offered
  • Dead pixels: ≤0.03% at acceptance, ≤0.1% at year 3

Performance language lets a good supplier propose a better or cheaper route and forces a bad one to either meet the number or declare that they cannot. That declaration is worth more than a low price.

Some facades do not use one family throughout — mesh on the main elevation, a linear profile along the roofline, pixel strings at the entrances. If yours is one of them, the architectural LED facade lighting range groups the families by surface and states the control and power architecture each one assumes, so the RFQ asks for the right system rather than three products that will not run off the same controller.

7. Fix the Commercial Terms Before the Prices Arrive

Bidding suppliers on price alone while leaving terms open produces a spread you cannot interpret. Put these in the RFQ as fixed requirements, not questions:

TermWhat to requireWhy it matters
IncotermName one: FOB, CIF, or DDP. Do not accept a mixFOB and DDP on the same scope can differ 12–18%
Currency and validityUSD or EUR, price held 60 daysFX movement on a 6-month project is real
Payment schedulee.g. 30% deposit / 60% before shipment / 10% after acceptance100% advance removes all your leverage
Production lead timeStated in working days from drawing approval, not from orderApproval can take 3 weeks
WarrantyYears, failure criterion, response time, who pays freight“5 years” alone means nothing
Acceptance test48–72 h full-power burn-in with records, plus on-site criteriaCheap quotes often skip burn-in
Liquidated damagesPer-week delay credit, cappedOptional, but it changes behaviour

One note on payment: a supplier who insists on 100% before production is telling you something about their cash position, which is itself a delivery risk on a project with a hard opening date.

8. Quantity, Spares and the Unit-Price Trap

Ask for the quote as a bill of quantities (BOQ) — every line priced, nothing bundled — and compare on delivered cost per square metre of finished screen, not on fixture unit price. The unit price is the easiest number to move and the least meaningful.

Worked example, simplified, for a 600 m² P25 mesh facade:

LineSupplier ASupplier BNote
Screen modules$92/m²$78/m²B is cheaper on fixtures
Control systemincluded$21,000 extraB quoted screens only
Power suppliesincluded$9,400 extraSame
Mounting brackets$14/m²not quotedAssumed to be your scope
Spares 4%includednot quotedZero-spares risk
Freight to RotterdamDDP includedFOB ShenzhenDifferent Incoterm
Delivered cost per m²$171$169 + unknown structureLooks equal, is not

Supplier B’s headline number is 15% lower and its delivered scope is undefined. That is the exact situation a twelve-point RFQ prevents.

Put the formula in the RFQ itself, so every bidder prices the same lines:

Total installed cost per m² = modules + control system + power supplies + subframe and brackets + cable and connectors + installation labour + access equipment + commissioning + spares (3–5%) + freight and duty

Any line a bidder leaves blank gets flagged rather than absorbed. That single instruction converts a price list into a comparison.

9. Reading the Responses: Green Flags and Red Flags

Once the quotes are in, the useful signal is in how each supplier answers the items you specified — not in the total. Six green signals and six red ones, and most first-round quotes carry at least one of each:

Green and red flags in a returned facade lighting quotation Reading a returned quote Six signals that a number can be trusted, six that it cannot. Green flags ✓ Each of the twelve items priced separately ✓ Assumptions stated where the brief was silent ✓ Test reports match the quoted model ✓ Reference project older than three years ✓ Names who attends site in your country ✓ Raises an objection to your spec, with a reason Red flags ✕ One lump sum, no breakdown ✕ Answers half the twelve, ignores the rest ✕ Warranty longer than its product history ✕ Cannot name the LED bin or driver brand ✕ Datasheet for a different model ✕ Discounts the moment you ask a question A supplier that cuts price the moment you ask it to explain something has priced the explanation out already.
Green and red flags in a returned facade lighting quotation.

Read the pattern, not the single line. Three green flags with one red deserves a clarification call; three red flags tell you what the project will feel like after the order.

The most reliable single signal is the last one on the right. A supplier that cuts price the moment it is asked to explain something has priced the explanation out of the original number.

10. A Realistic RFQ Timeline

Most buyers plan two weeks for the RFQ. It costs five to seven, and the bottleneck is almost never the supplier.

StepWorking daysWho is the bottleneck
RFQ document drafted from the twelve items2–3Buyer
Drawings and wind-load data assembled2–4Architect or facade consultant
Suppliers review and ask questions3–5Supplier
Quotes returned5–10Supplier
Technical clarification round3–5Both
Sample and control-system compatibility test10–20Both — start this in parallel
Contract and payment terms3–7Buyer’s commercial team

Two things compress this. Send the control-system compatibility question with the RFQ, not after the winner is chosen — protocol mismatches discovered at commissioning are the most expensive kind. And run sampling in parallel with commercial negotiation, because a sample that arrives after the contract is signed is not a sample, it is a fait accompli.

11. Five RFQ Mistakes We See Every Year

  1. Asking for “best price” instead of a scope. It invites a number that has already been optimised by removing things.
  2. Bidding 8–10 suppliers. Beyond four or five, response quality drops and nobody treats the RFQ seriously.
  3. Leaving the structure out. On a curtain-wall retrofit, mounting steel is frequently the second-largest line after the screen.
  4. No spares. The single line most often cut, and the one that costs most to add later.
  5. Comparing totals instead of scopes. Two totals 15% apart usually describe two different projects.

FAQ

What should an LED facade lighting RFQ include? At minimum: separate facade and screen areas, pixel pitch with viewing distance, daytime nits and night dimming, transparency and wind load, IP rating with corrosion class, control protocol, power distribution concept, mounting interface, quantities with 3–5% spares, delivery and commissioning scope, commercial terms including Incoterm, and acceptance criteria. Twelve items, one page each of drawings.

How many suppliers should I invite? Four to five. Enough to see a real spread in approach, few enough that each treats the RFQ as a serious opportunity. Ten-supplier tenders usually return three complete answers and seven fixtures-only prices.

Do I need a lighting designer before sending an RFQ? Not necessarily, but you need the performance numbers a designer would produce: pitch from viewing distance, nits from facade orientation, wind load from the structural engineer. If you have neither, ask each bidder to propose those numbers and compare the reasoning — that comparison is often more informative than the prices.

How long is a facade lighting quotation valid? Typically 30–60 days. Ask for a stated validity period in writing. Copper, aluminium and LED bin pricing all move, and a quote with no expiry date is a quote you cannot hold anyone to at the moment you need it.

Can you quote from drawings only, without a specification? Yes. Send the elevation, the curtain-wall section, the site photographs and the wind load, and we will return a scope with our assumptions written out for you to accept or correct. That document is usually the fastest route to a comparable tender, because it gives every other bidder the same baseline.

Should the RFQ include a responsibility matrix? Yes, and it is often the most valuable page in the pack. List the eight work packages — curtain-wall fixing, performance numbers, subframe, power distribution, control and content, site termination, commissioning, acceptance — and ask each bidder to mark what it takes. Differences between the returned matrices explain most of the price spread you see, and they surface double-scope and unowned scope before contract rather than during installation.


Product ranges

Related engineering guides


Send us the brief, get a scope back

Send your drawings, the wind load and the viewing distance, and we will return a line-by-line scope with every assumption stated — within one working day, before any price discussion. If your RFQ already exists, send it as it is and we will mark the items that will make the returned quotes incomparable.

Step 1 — see the LED mesh screen range or the full facade lighting range. Step 2 — send the brief for a scope review.

Project enquiry

Send your drawings. Get a specification you can defend.

Elevation DWG, facade area, closest viewing distance and site country — we reply within 48 hours with a fixture matrix, power and DMX topology, and a quotation. No price-only quotes.

5,000+ projects delivered · 40+ countries · ISO 9001 · CE / UL / RoHS

About MEKALEO

We are an LED media facade manufacturer based in Guzhen, China, running our own 8,000 m² factory. Founded in 2004. 5,000+ projects delivered across 40+ countries. ISO 9001 certified; products carry CE, UL and RoHS certification. Address: No. 398, Haizhou East Bank North Road, Guzhen Town, Zhongshan City — factory visits and live video audits welcome.


About the publisher

MEKALEO is the export brand of Guangdong Meidile Technology Lighting Co., Ltd., a manufacturer of outdoor LED facade lighting and LED media facades. Founded in 2004, the company has worked on exterior architectural LED systems for 22 years and runs its own 8,000 m² factory in Guzhen, Zhongshan, China, with in-house SMT, vacuum potting and an IP test chamber. To date: 5,000+ delivered projects across 40+ countries, 100+ patents, ISO 9001, and CE / UL / RoHS certified products.

About us · Talk to an engineer