Last updated: November 2026 | MEKALEO Engineering Team — LED media facade manufacturer since 2004
Three quotations for the same facade. One says $96,000, one says $141,000, one says $88,500. Nothing about the building changed between them. What changed is what each supplier assumed you wanted — and none of them told you what they assumed.
Quick answer: A comparable facade lighting quotation needs twelve inputs fixed in writing — facade and screen area separately, pixel pitch and viewing distance, daytime brightness, transparency and wind load, IP and corrosion class, control protocol, power distribution, mounting interface, quantities plus spares, delivery and commissioning scope, commercial terms, and acceptance criteria. Fix all twelve, and every supplier prices the same scope instead of their own assumption.
This is the normal outcome of a facade RFQ written as a shopping list. “800 m² of LED mesh screen, P25, IP66, please quote.” A supplier can answer that sentence truthfully and still leave out the controller, the power supplies, the mounting brackets, the spare modules, the sea freight, and the commissioning support. Six months later those omissions are change orders, and the cheapest quote becomes the most expensive project.
The fix is not more suppliers. It is a brief specific enough that every supplier prices the same scope. Below is the twelve-item structure we use when an RFQ arrives, followed by the drawings to attach, the commercial terms to lock, and how to read what comes back.
1. Why Most Facade RFQs Come Back Incomparable
A quote is only comparable if five things are identical across bidders: scope, specification, quantity, commercial terms, and exclusions. A typical RFQ fixes only the second one, and only partly.
Here is what we see in roughly nine out of ten first-round RFQs that land in our inbox:
| What the RFQ says | What the supplier is free to assume |
|---|---|
| “800 m² LED mesh screen” | Screen area or facade area? Finished screen at 24% transparency covers far more wall than 800 m² |
| “P25” | P25 at which brightness? 2,800 nits or 5,000 nits is a different bill of materials |
| “IP66” | Potted module only, or the connector and cable gland too? |
| “Complete system” | Does complete include control, power, structure, cabling, commissioning? |
| “Delivery to site” | Which Incoterm? FOB Shenzhen and DDP Rotterdam differ by 12–18% of order value |
| (no quantity of spares) | Zero spares quoted, or 5%? On a 40,000-module job that is a five-figure gap |
| (no warranty terms) | “5 years” against what failure criterion, with what response time? |
None of these are tricks. A supplier answering an incomplete brief has to guess, and each guess moves the number. The purpose of an RFQ is to remove the guessing, not to collect prices.
2. The 12 Items in a Quote-Ready RFQ
Print this as a checklist. Every item that is missing from your RFQ becomes a variable in the price.
| # | Item to specify | Why it changes the price | Commonly left out |
|---|---|---|---|
| 1 | Facade area and screen area, separately | Drives module count, structure, and freight volume | Screen area almost always |
| 2 | Pixel pitch and viewing distance | Pitch sets density, weight, and cost per m²; overspecifying is the #1 overrun | Viewing distance |
| 3 | Required daytime brightness (nits) | 2,800 vs 5,000 nits is a different LED bin and power budget | Night dimming requirement |
| 4 | Transparency target (%) and wind load | Transparency and structural rating trade against each other | Wind load (kPa) |
| 5 | Ingress protection and corrosion class | Coastal sites need marine anodising and a salt-spray report | Distance to coastline |
| 6 | Control protocol and content source | DMX512, SPI, or Art-Net; who supplies the media player | Who owns the content pipeline |
| 7 | Power distribution concept | Loopback, number of feed points, voltage-drop allowance | Cable runs and PSU locations |
| 8 | Mounting interface | Curtain-wall clip, steel subframe, or existing rail — structural steel is often 15–25% of the order | Who designs the bracket |
| 9 | Quantities plus spares percentage | Spares are priced once at order and again at year 4, at 3–5× the unit price | Spares entirely |
| 10 | Delivery, installation and commissioning scope | Who unloads, who terminates, who does the night calibration | Site supervision |
| 11 | Commercial terms | Incoterm, currency, payment schedule, liquidated damages | Incoterm and payment |
| 12 | Acceptance criteria | How the project is judged: brightness uniformity, dead-pixel rate, colour consistency | Dead-pixel threshold |
Two of these deserve a longer note, because they are where most money is lost.
Item 1 — area. Always give both numbers. If you specify “1,200 m² of facade” for a P25 mesh at 55% transparency, you will receive a quote for roughly 540 m² of screen plus a structure sized for the full elevation — and you will spend the first project meeting arguing about which number was agreed. State screen area, and state the facade area it must cover.
Item 9 — spares. Facade modules are not shelf items in most countries. If you order zero spares and lose 1.5% of modules to water ingress in year three, you are buying a small production run at prototype pricing plus air freight plus a crew with a crane. Specifying 3–5% spare modules and 2% spare power supplies at order time is the cheapest insurance in the whole budget.
Both figures start from the same specification: pitch, transparency and weight per m². Our LED mesh screen range publishes those numbers model by model, which is how you convert facade area into screen area and module count — and size the spare allowance before anyone quotes.
Mark every input: confirmed, proposed, pending
A detail worth copying from construction procurement: tag each field in the RFQ with its status, so a supplier knows what it may question and what it must not change.
| Status | Meaning | Supplier’s freedom |
|---|---|---|
| Confirmed | Fixed by the client, the consultant or a regulation | Must meet it; may object in writing with a reason |
| Proposed | A starting point the client will reconsider | Should propose better if it can, and explain why |
| Pending | Known to be missing; date expected | Must state the assumption it priced against |
| N/A | Not applicable to this project | Should not invent a scope item for it |
Without this, every gap looks the same, and suppliers fill gaps with whatever is cheapest for them. With it, a returned quote tells you exactly where the risk sits.
3. Who Is Responsible for What
The most common cause of a facade project running late is not a product failure. It is two parties each believing the other owned a work package. The RFQ is the right place to fix that, because it costs nothing to write down and a great deal to argue later.
| Work package | Who must own it | What goes wrong when it is unclear |
|---|---|---|
| Curtain-wall fixing design | Facade contractor or structural engineer | Bracket clashes with the mullion; load path never approved |
| Lighting performance numbers | Lighting designer, or the supplier if asked explicitly | Pitch and brightness decided by whoever quoted first |
| Structural subframe | Usually the installer; sometimes the supplier | Each side assumes the other, and the steel appears in no quote |
| Power distribution design | Electrical engineer, with supplier input on voltage drop | Too few feed points; visible dimming at run ends in year one |
| Control and content pipeline | AV or control integrator | Nobody owns the media player; commissioning stalls for weeks |
| Site termination of connectors | Specialist installer, or factory pre-termination | Site-terminated joints are where most ingress warranty claims die |
| Commissioning and night calibration | Supplier and installer jointly | Facade opens uncalibrated, with visible colour patches |
| Acceptance and baseline record | Owner or consultant | No baseline, so every later warranty claim becomes an opinion |
Copy this table into the RFQ and ask each bidder to mark what it takes. The answers are more useful than the prices, because they expose which bidder has actually delivered a facade before.
4. Submittals: What a Serious Bidder Sends Back
A price is not a submittal. Ask for these with the quote, not after the order, and the comparison stops being about totals:
- Mounting node drawing at the actual curtain-wall section, with fixing centres and torque values
- Photometric files — IES or LDT for every optic offered, so the designer can verify the numbers independently
- BIM object — a Revit family or CAD block at the mounting node, if the project has a BIM requirement
- Wiring diagram — feed points, PSU zones, loopback arrangement, cable schedule per run
- Test reports whose model numbers match the offered product: IP, salt spray, LM-80, and a 48–72 h burn-in record template
- Packaging data — weight and volume per m², because freight on a 600 m² facade is a five-figure line and it depends on how the modules are crated
- Warranty certificate draft, not a marketing claim about warranty
- Spare parts list with part numbers, so replenishment in year four is a purchase order rather than a re-engineering job
Two of these decide whether the project can be commissioned on schedule: the wiring diagram and the BIM object. They are also the two most often missing from a first-round quote.
5. Drawings and Data to Attach
Text alone cannot produce an accurate facade quote. Attach these four, in this order of importance:
- Elevation with dimensions, marked with the area to be covered, and any zone where lighting must stop (fire exits, signage, adjacent property).
- Curtain-wall or cladding section detail at the mounting line. This single drawing decides whether the job uses a clip system or a steel subframe — and that difference is often larger than the difference between two fixture suppliers.
- Site photographs from the likely viewing positions, taken at night if possible. They settle the pitch and brightness argument faster than any datasheet.
- Structural and environmental data: design wind load, distance to coastline, ambient temperature range, seismic zone if relevant.
If you do not have item 2, say so in the RFQ and ask each bidder to state their assumed mounting concept explicitly. An assumption written down can be compared; an assumption buried in a price cannot.
A fifth input is not a document. Ask each bidder to price a mock-up — a 2–4 m² panel at the real mounting condition, one module bay, one power feed, one controller channel. Pitch, brightness, transparency and colour are judged together there and nowhere else, and on design-review projects its approval is a contractual hold point. A supplier that has never built one prices it as an extra; one that builds them routinely tells you where the panel should go.
6. Specify Performance, Not a Brand and Model
There is a strong temptation to paste a competitor’s model number into the RFQ so everyone prices the same thing. It feels rigorous. In practice it gets you either an exact copy at a lower price with unknown LEDs inside, or a polite refusal from suppliers who will not clone.
Write the requirement as measurable performance instead:
- Brightness: 3,000 nits calibrated at 6,500 K, measured at module surface, with a night dimming floor below 300 nits
- Colour consistency: within 3 SDCM across the delivered batch
- Transparency: minimum 50% optical, measured on the installed module grid
- Ingress protection: IP66 on module and connector, verified by test report matching the offered model
- Salt spray: 500 h neutral salt spray to ISO 9227 for sites within 5 km of the coast
- Lifespan: L70 at 50,000 h, LM-80 data for the LED bin offered
- Dead pixels: ≤0.03% at acceptance, ≤0.1% at year 3
Performance language lets a good supplier propose a better or cheaper route and forces a bad one to either meet the number or declare that they cannot. That declaration is worth more than a low price.
Some facades do not use one family throughout — mesh on the main elevation, a linear profile along the roofline, pixel strings at the entrances. If yours is one of them, the architectural LED facade lighting range groups the families by surface and states the control and power architecture each one assumes, so the RFQ asks for the right system rather than three products that will not run off the same controller.
7. Fix the Commercial Terms Before the Prices Arrive
Bidding suppliers on price alone while leaving terms open produces a spread you cannot interpret. Put these in the RFQ as fixed requirements, not questions:
| Term | What to require | Why it matters |
|---|---|---|
| Incoterm | Name one: FOB, CIF, or DDP. Do not accept a mix | FOB and DDP on the same scope can differ 12–18% |
| Currency and validity | USD or EUR, price held 60 days | FX movement on a 6-month project is real |
| Payment schedule | e.g. 30% deposit / 60% before shipment / 10% after acceptance | 100% advance removes all your leverage |
| Production lead time | Stated in working days from drawing approval, not from order | Approval can take 3 weeks |
| Warranty | Years, failure criterion, response time, who pays freight | “5 years” alone means nothing |
| Acceptance test | 48–72 h full-power burn-in with records, plus on-site criteria | Cheap quotes often skip burn-in |
| Liquidated damages | Per-week delay credit, capped | Optional, but it changes behaviour |
One note on payment: a supplier who insists on 100% before production is telling you something about their cash position, which is itself a delivery risk on a project with a hard opening date.
8. Quantity, Spares and the Unit-Price Trap
Ask for the quote as a bill of quantities (BOQ) — every line priced, nothing bundled — and compare on delivered cost per square metre of finished screen, not on fixture unit price. The unit price is the easiest number to move and the least meaningful.
Worked example, simplified, for a 600 m² P25 mesh facade:
| Line | Supplier A | Supplier B | Note |
|---|---|---|---|
| Screen modules | $92/m² | $78/m² | B is cheaper on fixtures |
| Control system | included | $21,000 extra | B quoted screens only |
| Power supplies | included | $9,400 extra | Same |
| Mounting brackets | $14/m² | not quoted | Assumed to be your scope |
| Spares 4% | included | not quoted | Zero-spares risk |
| Freight to Rotterdam | DDP included | FOB Shenzhen | Different Incoterm |
| Delivered cost per m² | $171 | $169 + unknown structure | Looks equal, is not |
Supplier B’s headline number is 15% lower and its delivered scope is undefined. That is the exact situation a twelve-point RFQ prevents.
Put the formula in the RFQ itself, so every bidder prices the same lines:
Total installed cost per m² = modules + control system + power supplies + subframe and brackets + cable and connectors + installation labour + access equipment + commissioning + spares (3–5%) + freight and duty
Any line a bidder leaves blank gets flagged rather than absorbed. That single instruction converts a price list into a comparison.
9. Reading the Responses: Green Flags and Red Flags
Once the quotes are in, the useful signal is in how each supplier answers the items you specified — not in the total. Six green signals and six red ones, and most first-round quotes carry at least one of each:
Read the pattern, not the single line. Three green flags with one red deserves a clarification call; three red flags tell you what the project will feel like after the order.
The most reliable single signal is the last one on the right. A supplier that cuts price the moment it is asked to explain something has priced the explanation out of the original number.
10. A Realistic RFQ Timeline
Most buyers plan two weeks for the RFQ. It costs five to seven, and the bottleneck is almost never the supplier.
| Step | Working days | Who is the bottleneck |
|---|---|---|
| RFQ document drafted from the twelve items | 2–3 | Buyer |
| Drawings and wind-load data assembled | 2–4 | Architect or facade consultant |
| Suppliers review and ask questions | 3–5 | Supplier |
| Quotes returned | 5–10 | Supplier |
| Technical clarification round | 3–5 | Both |
| Sample and control-system compatibility test | 10–20 | Both — start this in parallel |
| Contract and payment terms | 3–7 | Buyer’s commercial team |
Two things compress this. Send the control-system compatibility question with the RFQ, not after the winner is chosen — protocol mismatches discovered at commissioning are the most expensive kind. And run sampling in parallel with commercial negotiation, because a sample that arrives after the contract is signed is not a sample, it is a fait accompli.
11. Five RFQ Mistakes We See Every Year
- Asking for “best price” instead of a scope. It invites a number that has already been optimised by removing things.
- Bidding 8–10 suppliers. Beyond four or five, response quality drops and nobody treats the RFQ seriously.
- Leaving the structure out. On a curtain-wall retrofit, mounting steel is frequently the second-largest line after the screen.
- No spares. The single line most often cut, and the one that costs most to add later.
- Comparing totals instead of scopes. Two totals 15% apart usually describe two different projects.
FAQ
What should an LED facade lighting RFQ include? At minimum: separate facade and screen areas, pixel pitch with viewing distance, daytime nits and night dimming, transparency and wind load, IP rating with corrosion class, control protocol, power distribution concept, mounting interface, quantities with 3–5% spares, delivery and commissioning scope, commercial terms including Incoterm, and acceptance criteria. Twelve items, one page each of drawings.
How many suppliers should I invite? Four to five. Enough to see a real spread in approach, few enough that each treats the RFQ as a serious opportunity. Ten-supplier tenders usually return three complete answers and seven fixtures-only prices.
Do I need a lighting designer before sending an RFQ? Not necessarily, but you need the performance numbers a designer would produce: pitch from viewing distance, nits from facade orientation, wind load from the structural engineer. If you have neither, ask each bidder to propose those numbers and compare the reasoning — that comparison is often more informative than the prices.
How long is a facade lighting quotation valid? Typically 30–60 days. Ask for a stated validity period in writing. Copper, aluminium and LED bin pricing all move, and a quote with no expiry date is a quote you cannot hold anyone to at the moment you need it.
Can you quote from drawings only, without a specification? Yes. Send the elevation, the curtain-wall section, the site photographs and the wind load, and we will return a scope with our assumptions written out for you to accept or correct. That document is usually the fastest route to a comparable tender, because it gives every other bidder the same baseline.
Should the RFQ include a responsibility matrix? Yes, and it is often the most valuable page in the pack. List the eight work packages — curtain-wall fixing, performance numbers, subframe, power distribution, control and content, site termination, commissioning, acceptance — and ask each bidder to mark what it takes. Differences between the returned matrices explain most of the price spread you see, and they surface double-scope and unowned scope before contract rather than during installation.
Product ranges
- LED mesh screen — pixel pitch, transparency, nits and IP rating by model
- Architectural LED facade lighting — mesh, linear and pixel systems in one range
Related engineering guides
- Media facade lighting cost guide (2026): pricing and cost per m²
- Outdoor LED media facade cost: what drives price per square metre
- How to vet a media facade manufacturer before you spend a dollar
- Media facade lighting buying guide: types, costs and how to choose
- LED pixel pitch and viewing distance: the formula
- LED mesh facade voltage drop and signal delay
Send us the brief, get a scope back
Send your drawings, the wind load and the viewing distance, and we will return a line-by-line scope with every assumption stated — within one working day, before any price discussion. If your RFQ already exists, send it as it is and we will mark the items that will make the returned quotes incomparable.
Step 1 — see the LED mesh screen range or the full facade lighting range. Step 2 — send the brief for a scope review.
Project enquiry
Send your drawings. Get a specification you can defend.
Elevation DWG, facade area, closest viewing distance and site country — we reply within 48 hours with a fixture matrix, power and DMX topology, and a quotation. No price-only quotes.
5,000+ projects delivered · 40+ countries · ISO 9001 · CE / UL / RoHS
About MEKALEO
We are an LED media facade manufacturer based in Guzhen, China, running our own 8,000 m² factory. Founded in 2004. 5,000+ projects delivered across 40+ countries. ISO 9001 certified; products carry CE, UL and RoHS certification. Address: No. 398, Haizhou East Bank North Road, Guzhen Town, Zhongshan City — factory visits and live video audits welcome.